Problems and solutions in the construction of pile foundations

This article discusses pile foundation problems and solutions for them. Pile foundations are a broad field that needs to be studied in detail to identify the deficiencies of the structure.

However, when constructing piles, there is an important aspect that must be considered and taken into account to avoid major problems in construction.

We cannot observe with the naked eye the state of the pile or what is happening underground. What we can do is follow proper construction procedures to ensure quality control and assurance.

Even though Pile Foundations are designed by an expert, the pile can fail if constructed incorrectly.

Let's discuss each of the design questions in detail.

Stack Tray

One of the most important works that must be carried out at the beginning of the construction of a pile.

If it goes wrong, everything we do will be subject to the original error.

It is true that we cannot always maintain the accuracy of the implantation as precisely indicated in the drawings. However, we must at least ensure that the tolerance limit is respected.

Most guidelines specify the pile construction tolerance as 75 mm. However, different guidelines specify different ranges depending on the type of construction.

The following table lists the tolerances allowed in the project.

code Allowed tolerance
ACI-336 4% of the diameter or 75 mm, whichever is smaller
EN 1536 standard 100mm; for pile diameter (D) ≤ 1000 mm

0.1D to 1000

150mm D>1500

Design for a tilt angle of less than 1 in 15, limited to 20 mm/m

Version with inclination between 1 in 4 and 1 in 15, limited to 40 mm/m

KP4 – The big goal 75mm
BS 8004 No more than 1 in 75 vertically or 75 mm

For bored piles with an inclination angle of up to 1 in 4, a deviation of up to 1 in 25 is allowed.

If the pile tolerance is within limits, the pile design is accepted. The building designer must consider the acceptable tolerance in his design.

For example, if the allowable tolerances for pile deviation are 75 mm, the superstructure must be designed accordingly. We cannot change the column position by moving the post.

So we need to design the floor beam to support the column loads when there are two piles or just one pile. If there are three or more piles, this can be taken into account for the piles and an increase in the pile load due to movement towards the support must be taken into account when assessing the pile capacity.

If the deviation is greater than the limit allowed for the arrangement of piles in the block, it must be checked after construction and the necessary adjustments made. The designer should design the floor joists for eccentricity as much as possible, check the increase in pile capacity by moving the piles, check the block plates for new eccentricity, etc.

Digging piles and anchors

When excavating or drilling piles, we must take several aspects into consideration.

Let's discuss each of them.

  • Steel case deviation

Steel casing is used when the soil is very weak and collapse cannot be absorbed by the bentonite fill. The depth of the enclosure can reach the end of soft soil such as peat.

The center of the box may vary when placed as it collapses during placement. Even if the center of the box is checked after placement, it may be crooked.

Furthermore, during excavations, the lining may deviate from its original position because the soil does not have sufficient transverse rigidity.

This could be avoided by inserting the lining into the hard soil layer to a suitable depth and checking the position of the lining before and after concreting.

Tolerances can be checked against the relevant standard or as indicated in the table above.

  • Excavation collapse

When building pile foundations, soil collapse is inevitable. However, it can be minimized by controlling the density of the bentonite suspension.

Regular checks must be carried out to ensure that the density is within acceptable limits.

  • Lots of water in the pile

As excavation continues beyond the water table, water will seep into the excavation pit.

The bentonite level must be checked regularly to prevent water from entering the post. Since the density of bentonite is higher, there is less chance of water movement.

Additionally, the density of the bentonite should be checked regularly and necessary adjustments made as necessary to maintain the required density of the bentonite.

  • Lateral movement and lifting of adjacent piles

In general, the distance between piles is approximately 2.5 to 3 times the diameter of the pile.

When driving into pile casings, there is a possibility that the surrounding piles will move.

This must be done very carefully and lateral movements can be minimized or avoided.

  • settlements

Driving the piles causes excessive vibrations in the ground.

Even though this keeps vibrations within acceptable limits, the effects of vibrations can lead to settlement of adjacent structures.

Particularly for structures built on shallow foundations, settlement can occur during pile foundations. Furthermore, excessive vibration can cause serious problems.

As the structure settles, cracks can occur and even the old structure or improperly constructed structures can collapse.

For this reason, vibrations due to the design must be minimized as much as possible. The use of new tools, electric drills, etc. can reduce vibration.

  • With sufficient base and termination

The embedment depth is indicated in the pile design drawings. However, determining the starting and ending points of the embedding depth is a challenging task.

The embedment depth of a pile is determined based on several factors. Some of these are information from the well log, rate of penetration into the rock, observation of rock samples, etc.

Additionally, on-site tests such as Point Load Testing could be carried out to determine the strength of the rock. It may be related to the bearing capacity of the rock. This way we can determine the condition of the rock and decide on termination accordingly.

  • Poor cleaning of the pile tip

It is essential to clean the battery properly. Cleaning the pile is called rinsing.

This can be done based on parameters determined through the bentonite test. The top of the bet is not visible. Therefore, we decide whether to clean the pole.

The bentonite is removed from the excavation pit and mechanically cleaned, removing the washed sand and mud. It is pumped from the top of the excavation pit. The bentonite is removed from the base of the post for cleaning.

This process continues until it is ensured that there is no more mud/sand in the bentonite.

During the washing process, among other things, the balance of the sludge, the balance of the reservoir and the sand content are checked.

Properties for bentonite suspensions
Property Unit stages Test Equipment
Fresh Ready to reuse Before concreting
density g/ml <1.10 <1.25 <1.15 Mud balance
Marsh Viscosity (946 ml) second 32-50 32-60 32-50 Swamp funnel
Sand content % N/A N/A <4 Sand content
pH 7 to 11 7 to 12 n/a PH meter

The ranges specified in the table above can be respected before concreting. Values ​​may vary from specification to specification. The date can be found in the project specification.

Concreting problems

Problems commonly observed during construction are highlighted below.

  • If the concrete is strong enough

Generally, piles are cast in grade 30 concrete. This value may vary from country to country.

Insufficient compressive strength of the concrete in the pile leads to serious design problems.

As the pile is an underground structure, correction is very difficult. If the actual load exceeds the bearing capacity of the pile, additional piles may be erected.

  • Voids in concrete

Since the self-compacting concrete is poured into the pile, no vibration is required. Furthermore, due to the depth of the pile, it is very difficult to vibrate the concrete to achieve better agitation.

Due to design problems, voids may appear in the pile. This may be due to poor concrete quality and inconsistent workability of concrete.

Regular inspection and monitoring of concrete quality could prevent these problems.

  • Mix concrete with bentonite

The concrete is poured so that it does not mix with the bentonite.

First, the contractor is placed in the slot of the bored pile. Then the concrete is poured at the contractor. The contractor is then slowly lifted so the concrete can flow.

The contractor is then filled with concrete again. The contractor is then slightly elevated so that the concrete can gradually flow. This process continues with the concreting of the pile.

The contractor's end is always in the fresh concrete and we never elevate the contractor to the top level of the concrete pile when pouring the concrete.

We are trying to get to the end of this Embed the contractor at least 1-1.5 m into the fresh concrete avoid mixing fresh concrete with bentonite.

  • Bulges and constrictions

During the construction phase, concrete can swell or contract.

Cold tapering the pile exposes the reinforcing cage and reduces the cross-sectional area of ​​the pile.

A reduction in the cross section of the pile leads to a reduction in the bearing capacity of the pile.

  • Temperature increase in concrete

The temperature rise of the pile must be checked at least at the beginning of the pile construction.

The first pile could be checked using the strain gauges and temperature fluctuations could be monitored.

Based on the results of the data analysis, specific adjustments can be made.

Reinforcement cage movement

  • Raising the reinforcement cage

At high concreting speeds, the reinforcing cage may lift. The concreting process must therefore be carried out in a controlled manner.

Once the container has been raised, we can no longer lower it. Raising the cage beyond the embedment length causes serious problems in pile construction.

This may result in the stack being abandoned.

  • Lack of reinforcement cover

Lateral movement of the reinforcement cage may result in its lateral exposure. This may be due to the ground collapsing on one side of the pile excavation.

Conteúdo Relacionado

Slab foundations are types of foundations used in the...
Concrete cracks and concrete crack repair are very common...
Due to their advantages over other types of panels,...
It seems that there is no structure without cantilevers....
Depending on the type of construction, different types of...
Welding testing is used to determine the quality of...
No structure is built without construction joints. Concrete construction...
The special properties of hardened concrete are the main...
As the name suggests, destructive weld testing is performed...
Non-destructive testing of welds is more common and generally...
Different types of panels are constructed for shelter or...
Cold joints in concrete structures can occur due to...
The concrete slump test is a measure of the...
This article discusses the tallest buildings in the world....
Before the final inspection before concreting, an inspection of...
Knowing how to compact the soil is very important...
A wall that supports both its own weight and...
Column strengthening methods are discussed in detail. Improvement or...
This article explains the method of reinforcing concrete beams....
As civil engineers, we need to be aware of...
Back to blog

Leave a comment

Please note, comments need to be approved before they are published.